An analysis of the mammoth data centre proposed by celebrity investor Kevin OâLeary suggests it would release the equivalent of 23 atom bombs of heat waste into the boreal forest of northwestern Alberta every day.
If the Wonder Valley project goes ahead, ââabout 23 Hiroshima-sized atomic bombs worth of energy every single day will get dumped into that landscape,â said Utah State University physicist Robert Davies.
âThe effect will almost certainly be large, if not extreme,â said Davies, who conducted a preliminary analysis for the Sturgeon Lake Cree Nation (SLCN) earlier this year.Â
In September, the nation filed for a judicial review of the projectâs exemption from a provincial environmental impact assessment.
“I can’t imagine allowing it to go forward without those full assessments,â Davies said, describing the projectâs potential to be âthe largest single-site heat source on the entire planet.â
OâLeary Digital Limitedâs $70-billion data centre is proposed for the Municipal District of Greenview, south of Grande Prairie and roughly 130 kilometres southwest of SLCNâs reserve, in the First Nationâs traditional territory.
Updated info about water use, timelines for proposed Wonder Valley AI project in Alberta
Northern Albertans raise concerns about Wonder Valley AI data centre at packed community hall
‘We have serious concerns,â northern Alberta chief says after hosting community meeting on Wonder Valley
At full operation, it would release around 18 gigawatts of heat a day and about 30 million tonnes of carbon dioxide a year â more than four per cent of Canadaâs total emissions, said Davies, whose assessment was based on publicly available information.
âWhen people talk about environmental regulations that these projects have to adhere to, those regulations were not created with anything of this scale in mind.âÂ
SLCN filed the judicial review application in September and requested another review in court last month to demand more consultation before the project can go ahead.
Wonder Valleyâs unprecedented scale warrants more rigorous discussion, said SLCNâs lawyer, Orlagh OâKelly.
In a Oct. 30 statement, Albertaâs Ministry of Environment and Protected Areas said it followed the established legal process to determine that no environmental impact assessment (EIA) was required for the project.Â
EIAs âare typically required when a project, or components of a project, involve technologies or systems with unknown environmental impacts. In this case, the project uses standard, proven power and water systems that have been safely used in Alberta for decades,â the statement said.
âEven when an EIA is not triggered, proponents must still obtain all required permits, provide detailed technical assessments on impacts to air, land, and water, and demonstrate the project can be built and operated safely before any project can proceed.â
Will Metaâs data centre raise Alberta power bills? Experts say it could
UCP fall agenda prioritizes ‘merit’ hiring, data centres, standardizing report cards
Proposed data centre in west-central Alberta prompts pushback from some residents, support from others
The permitting process canât measure the entire impact of a project, Davies countered.Â
âPermits check the parts. An assessment checks the whole. A project this size is exactly what assessments are for.â
The Ministry of Indigenous Relations said it is unable to comment on the review regarding consultation, while the matter is before the courts.
Along with the province, the M.D of Greenview and OâLeary Digital are also named as respondents in SLCNâs filings.
âWe also respect the robust and stringent regulatory process we must follow in advancing Wonder Valley,â OâLeary Digital CEO Paul Palandjian wrote in an Oct. 27 email. âMeanwhile, weâre having productive dialogue with Indigenous communities through consultation and engagement, and we remain committed to that work.”
Greenview Reeve Ryan Ratzlaff said the district always pursues development in a âresponsible, respectful and collaborative manner,â noting that environmental oversight and Indigenous consultation fall under the purview of the Alberta government.
A new sign, installed earlier this year, sits along Highway 40 at the entrance to the Greenview Industrial Gateway which would be the home of Wonder Valley if the project is green-lit. (Eagle Andersen/CBC)
SLCN is also in the midst of another court battle with OâLeary Digital, after a judge dismissed the companyâs bid to strike down a judicial review on consultation and water rights, which initially went in the nationâs favour.
OâKelly said the current system forces First Nations to file legal challenges to be heard, calling it “deliberately bifurcated and piecemeal.”
Chief Sheldon Sunshine said SLCN has built productive relationships with other oil and gas developers, but the nationâs experience with Wonder Valley has been difficult  since it was announced.
âIf anybody’s to learn anything about this â this is the project that went the absolute wrong way.â