The Albertan government says it is proposing more restrictions on data centres in response to Albertans’ concerns.
If passed, Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, would establish minimum distances between data centres and homes and stricter protections for water and farmland.
“Over the last several months, we’ve heard from Albertans and municipalities that they still have questions and they still have concerns,” Nate Glubish, minister of technology and innovation, said in a news conference on Wednesday.
“The changes we are proposing today, if adopted, will ensure that Alberta has the highest standards in all of North America for what responsible development looks like.”
The bill would restrict data centres that draw 10 megawatts or more of power from being built within 600 metres of the nearest home or on Alberta’s highest-quality farmland, Glubish said, noting that the Alberta Utilities Commission (AUC) would be the regulatory body overseeing the facilities.
Roughly 14 million acres of land is considered highest quality, including Class 1 and 2 farmland plus Class 3 land in municipalities without Class 1 or 2 soil.
Large data centres would also be prohibited on irrigated land, due to its importance to the province and the significant investment needed to bring water there, Glubish said.
He noted that designated industrial zones such as the Alberta Industrial Heartland and the Greenview Industrial Gateway, as well as existing brownfield sites, could be exempt from the setback rules since they are intended for heavy industrial use.
Municipalities could also reduce the 600-metre setback if affected landowners and the AUC agree.
The province said about 30 per cent of current data centre proposals would likely be affected by the changes.
Alberta has emerged as a frontrunner in Canada for proposed projects, with several already at various stages of development, including the Meta Sturgeon Data Centre in Sturgeon County, Beacon Indus Data Centre Hub in Rocky View County, Malachite One in Yellowhead County and Mihta Askiy Data Centre in Northern Sunrise County.
As of last month, companies proposing data centres had submitted more than 25,000 MW worth of grid connection requests to the Alberta Electric System Operator (AESO), exceeding Alberta’s all-time provincial peak electricity demand of 12,800 MW.
The projects aim to feed the growing worldwide appetite for artificial intelligence.
Meta Platforms Inc., the tech giant behind Facebook and Instagram, announced plans in July to build a $13-billion data centre complex, expected to be online in two to three years. The amendments will not apply as it was already approved.
“Sturgeon County is encouraged by the progress on regulatory frameworks for data centre development that protect agricultural land and water,” said Mayor Alanna Hnatiw, in a news release.
“Sturgeon County will continue to advocate for action on cumulative effects on transportation infrastructure, emissions, stakeholder engagement, responsible use of artificial intelligence, digital privacy and digital sovereignty.”
Data centres have prompted significant concerns and conversation in Canada and around the world.
Polling commissioned by CBC News in September found that many Albertans are skeptical about the centres, voicing concern around environmental and energy impacts.
This includes their dependency on the electricity grid and the possible implications on the average Albertan’s energy bill, as well as impacts on water usage and noise.
Bill 42 includes amendments that target water usage concerns and would require data centres to use close to zero water for cooling, and to recover any waste heat for use by greenhouses, industry or homes.
Existing power-plant noise limits would also be extended to include the facilities.
The CBC poll found only seven per cent of respondents strongly support the development of data centres, while 31 per cent strongly oppose it.
Some 26 per cent mostly oppose data centres, but believe some should be built. The resistance crosses geographical and partisan lines, the polling suggests.
A recent Harvard study on data centres in the United States found the 400 largest data centres in that country put more heat-trapping gases into the atmosphere in one year than the entire nation of Denmark.
Glubish also announced that to address pollution concerns, Bill 42’s amendments would increase maximum fines for serious environmental contamination to $6 million for corporations, including data centre operators, in addition to existing cleanup and remediation obligations.
In August, the AUC denied an application to build a natural gas plant that would have powered a massive data centre complex in the small agricultural town of Olds, Alta.
The commission found that the project by Synapse Real Estate Corp. would be too close to the surrounding community, and that “Synapse failed to demonstrate any compelling justification for selecting that location.”
Glubish said that rejection is an example of the province’s strict regulation of data centres.
“This will give communities like Olds that confidence that this can never happen in their backyard, and they don’t have to wait for months and months and months for a regulatory process to unfold,” he said.
“They will just know that AUC will not even consider an application that is inside of those boundaries. We think this is the right balance, and that this is going to ensure that responsible development can proceed.”
In Wednesday’s news release, Olds Mayor Dan Daley said the proposed measures appear to strike a reasonable balance between protecting communities and the power Albertans rely on while providing clarity for projects with the potential to bring lasting benefits.